Project scope

For the removal of Wintershall’s K10-B jacket in the Dutch North Sea, heavy-lift contractor Scaldis contracted DECO Subsea for the final cutting before the heavy lift. The jacket piles had to be cut internally below seabed level, which first meant clearing the stiff clay inside the piles.


For this, DECO Subsea built a bespoke clay cutter dredge, nicknamed “Hannibal Lecter”. High-pressure water jets cut into and penetrate the clay layer, after which cutting teeth scrape away the weakened clay. With the piles dredged, a bespoke internal cutting robot wedged itself inside the pile and made the cut below seabed using ultra-high-pressure (UHP) abrasive waterjet cutting.


Combining UHP technology with established dredging techniques proved successful. The dredge can also be adjusted for cleaning work: high-pressure water jets are mounted around the circumference of its main plate. The “Hannibal Lecter” dredge has since been superseded by “Maurice”, DECO Subsea’s patented successor.

Red offshore oil rig against a blue sky, covered in barnacles and rust.

ISO 9001 and ISO 45001 certified.


DECO Subsea prides itself in working closely with its clients to develop a bespoke and innovative solution. DECO Subsea's services are designed for seamless integration in offshore project workflows.

DECO Subsea is ISO 9001 and ISO 45001 certified and an active member of Decom North Sea.